PHOTO / ©AVIATIKTAG |
The IAF currently has 114 HAL HPT-32 Deepak basic trainers, all grounded since July 2009 owing to critical technical problems and flight safety issues. In a Parliamentary Standing Committee report released this week, the MoD gave testimony saying, “The Air Force is procuring 75 Basic Trainer Aircraft (BTA) for its Stage-I (ab-initio) flying training requirement. PC-7 Mk-II Turbo Prop aircraft of M/s Pilatus, Switzerland has been short-listed and contract negotiations have been completed. The case is being processed for CCS approval. The delivery of the aircraft is scheduled to commence 15 months after signing of the contract. 24 aircraft are expected to be delivered within 25 months, which will enable basic training to commence on these new aircraft. Two simulators for BTA are planned to be procured. 106 BTA are planned to be designed and developed by HAL along with 3 simulators. Induction is planned to commence from 2016.”
Speaking of the HPT-32 grounding and the genesis of the basic trainer procurement programme, the IAF told the Committee. “In July, 2009, we had a very unfortunate accident on the HPT-32, which was our basic trainer. This involved two very senior qualified Flying Instructors.About the HPT-32, because of no satisfactory response from the original equipment manufacturer of the engines, we found that we had no option but to ground those aircraft till such time we did get a very satisfactory answer. This aircraft has got a very adverse gliding characteristic. In case, the aircraft is not able to restart the engine in the air, then it is very dangerous for pilot. Here, we had two senior qualified Flying Instructors not able to pull off a safe landing. So, the Air Force had no option but to ground these aircraft. The process of getting this basic trainer aircraft started immediately thereafter.”
Speaking of the Korean protest and certain “anonymous” complaints, the IAF’s testimony continues: “Finally, there were only three aircrafts, which were short-listed. This entire process finished in January 2011 on approval of the Staff Evaluation Report by the Ministry. What happened after that was this. There were a couple of letters. There were some anonymous letters, some actual representations from one of the losing vendors. Therefore, it was felt appropriate in this case to have it thoroughly examined and the Ministry did that. It took some time. So, if you look at it, the time lost was, actually after submission of the report in 2011. If this had not interfered with the procurement process, I believe by end of 2011, by the last quarter, we would have certainly signed the contract. The intervening delay was only because of this reason.”
@Shiv Aroor
there are reports that Pilatus PC 7 is far less performer than KT 1 which is more powerful in terms of engine and capability.
whats your say
thanks
Joydeep Ghosh
very good but so late it sent massage to other company we know britian strongly stand faver for typhoon aginst rafle
whichever or whatever aircraft that has been selected please pass the deal at the earliest.
It is good that a hurdle has been removed. Moreover the delivery appears to be slow, so if possible best efforts shall be made to expedite them.
Slowing down the development program of IJT Sitara is a crime. All over the world accidents occur during development of an aircraft. It should not be reason for slowing down. Nothing is better than indigenous trainer aircrafts. This has been experienced by IAF due to problems with British AJT Hawk.
DRDO/HAL must expedite the IJT Sitara program.
Has the Pilatus contract been signed yet?